Update from Atamora Feb 2015


WP_20150223_008Dear FR Dick


Work is progressing. Although not as fast as we wanted

because of financial constraint. We have finished the twelve bags of cement I bought last week. The initial twenty bags I budgeted will not do.

The work load was tiring us down and just at the time I was going to stop to take a few days rest, potters from Ogun state arrived on Saturday to help boost the man power for a week. See group photo by the two jeeps. You can see me smiling. The hand of God brought potters to help.

We are making progress now. The Hammer mill will commence work on Friday. We will begin milling
five tons of clay and sawdust to the right grain size. The Hammer mill is not bolted down like the mixers but mounted on a frame with the drive.
we conclude the low walls tomorrow and cast the top for strength and sitting.